Florida's Trusted Flooring & Remodeling Contractor · Free In-Home Estimates

Kitchen Remodeling · 11 min readHow-To

The right order of operations for a kitchen remodel.

A Florida kitchen remodel runs in a fixed order because the FBC dictates it: design, permit, demolition, rough electrical/plumbing/mechanical, then a mandatory rough-in inspection before any drywall closes, followed by drywall, flooring, cabinets, countertops, appliances, and a final inspection. Cabinets always precede countertops because a fabricator cannot template a slab until the cabinet boxes are set and level — a step that adds roughly two weeks of fabrication mid-project. Skip the sequence and you fail an inspection or rip out finished work.

Kitchen Remodeling By · Editorial Lead
A Florida kitchen remodel mid-sequence with cabinets set and countertops awaiting template over a finished floor

Watch

Kitchen Remodel Order of Operations in Florida Homes

Why the Remodel Order Is Fixed

The order of a Florida kitchen remodel is not a matter of taste — it is set by two hard constraints. First, the FBC requires that concealed work be inspected before it is covered, so rough wiring and piping must pass an inspection before drywall closes the walls. Second, stone countertops are templated off the cabinets after they are installed and leveled, which forces cabinets ahead of counters every time.

Get the sequence wrong and one of two things happens: an inspector red-tags work that was covered too early and you open the wall back up, or a fabricator arrives to template and finds no cabinets to measure from. Both reset the schedule. A remodel that respects the order moves in one direction only — nothing finished gets undone.

The Full Sequence at a Glance

A standard Florida kitchen remodel moves through eleven phases. The diagram below maps them on a timeline and marks the single inspection gate that everything before drywall must clear, plus the two-week fabrication gap that sits between setting cabinets and setting countertops.

FLORIDA KITCHEN REMODEL — BUILD SEQUENCE 1 Design 2 Permit 3 Demo 4 Rough-in EPM INSPECTION GATE rough-in passes before drywall 5 Drywall 6 Floor 7 Cabinets ~2-WEEK GAP template then fabricate 8 Countertops 9 Backsplash 10 Appliances 11 FINAL INSPECTION
The yellow gate is the FBC rough-in inspection — nothing covers a wall until it passes. The burnt block is the two-week countertop fabrication window that begins only after cabinets are set.

Two markers on that timeline are non-negotiable in Florida: the inspection gate after rough-in, and the fabrication gap after cabinets. Everything else can flex by a day or two, but those two govern the whole project's calendar.

Phase 1-2: Design and Permit

Design locks the layout, the cabinet specification, the appliance list, and the electrical and plumbing plan before a single tool comes out. In Florida this stage also determines whether you need a permit at all, because the scope of work decides that — not the room.

What design has to settle before demo

Final design fixes every dimension a trade will rely on later: cabinet runs, the sink and range locations, the island footprint, and where each receptacle and circuit lands. Because countertops are templated off cabinets, the cabinet layout is effectively the master drawing for the back half of the job.

Cabinet specification
Box material, sizes, and exact wall positions. In Florida's humidity, box material matters — see our take on kitchen cabinet box materials for plywood versus particleboard.
Electrical plan
Circuit count and receptacle placement to NEC Article 210.52. A kitchen needs at least two 20-amp small-appliance circuits, and no point along the countertop may sit more than 24 inches from a receptacle.
Plumbing and venting plan
Sink, dishwasher, and any island plumbing, plus the drain-waste-vent layout the rough-in inspection will check.

When a Florida kitchen remodel needs a permit

Permitting in Florida follows the scope of work. Touching the electrical, plumbing, mechanical, gas, or structural systems triggers a building permit and the inspection series that comes with it. A purely cosmetic refresh that leaves the utilities alone usually does not.

  • Permit typically required: adding or moving circuits and outlets, relocating the sink or adding island plumbing, removing a wall, or moving a gas line.
  • Permit often not required: replacing cabinets in the same footprint without touching utilities, swapping countertops, or installing a backsplash.
  • Always jurisdiction-specific: the threshold varies by city and county, and HVHZ jurisdictions in Miami-Dade and Broward apply stricter review.

When the work is permittable, a licensed contractor pulls the permit and owns the inspection schedule. Many homeowners hand this to a general contractor through permit handling and plan submittal rather than navigate the building department alone.

Phase 3-4: Demolition and Rough-In

Demolition strips the kitchen back to studs, subfloor, and slab so the trades can work in open walls. Rough-in is the phase where electricians, plumbers, and HVAC installers run everything that will later disappear behind drywall — and it is the phase the first inspection is built around.

What demolition exposes

Tearing out old cabinets, finishes, and sometimes flooring reveals what the design assumed. In older Florida homes this is where surprises surface: corroded supply lines in coastal areas, aluminum branch wiring, or a slab that is out of level enough to need attention before cabinets can sit true.

The three rough trades

Rough-in covers the concealed portion of each system. Each trade installs its lines and boxes to plan, ready for inspection, then stops short of finish work until the walls are closed.

  1. Rough electrical. Branch circuits, boxes, and home-run wiring to the panel, sized and placed to the NEC plan, including the dedicated and small-appliance circuits a kitchen requires.
  2. Rough plumbing. Supply and drain-waste-vent piping for the sink, dishwasher, and any island, pressure-tested and ready to inspect.
  3. Rough mechanical. The range-hood duct and any HVAC changes. A hood exhausting more than 400 cfm must be provided with makeup air under FBC Residential Section M1503.4, so the duct path is set now.

Because all three trades feed a single rough-in inspection, they are coordinated to finish together — a plumber leaving one untested vent line can hold up the electrician and the whole drywall phase.

Coordinating the trades to one inspection

A general contractor stages the three rough trades so their work is complete on the same day, then books a single inspection rather than three. That coordination is the difference between drywall starting on schedule and the job idling while one trade catches up.

Free In-Home Estimate

Want the sequence handled for you?

A Pro Work Flooring project director maps the full schedule, pulls the permit, and books every inspection in order.

The Inspection Gate Before Drywall

This is the pivot of the entire remodel. Under the FBC, the rough electrical, plumbing, and mechanical work must be inspected and approved before any wall or ceiling membrane is installed. The official language is consistent across jurisdictions: rough-in must pass prior to concealment.

What the inspector is verifying

The rough-in inspection confirms that the concealed systems are safe and to code while they are still visible. Once it passes, drywall can close the walls; until it passes, nothing covers them.

Electrical rough-in
Wire sizing, circuit protection, grounding, box-fill, and device placement — checked against the NEC plan.
Plumbing rough-in
Pipe materials, slope, venting, and a pressure test on the water and drain-waste-vent system.
Mechanical rough-in
Duct routing and the makeup-air provision for a high-cfm range hood.

The close-in that follows

With rough-in approved, insulation and drywall go up and the kitchen starts to look like a room again. In many Florida jurisdictions an insulation inspection precedes drywall; the framing inspection must be approved before insulation is covered. Drywall is taped, finished, and primed, creating the clean, plumb surfaces that cabinets and tile need.

Why drywall has to be flat and plumb here

Cabinets fasten to the wall and tile is set against it, so a wavy or out-of-plumb surface telegraphs straight into the finished kitchen. Closing in with a properly finished, primed wall is what lets the cabinet and countertop phases hit tight tolerances later.

Phase 5-8: Floors, Cabinets, Countertops

This is the finish run, and its internal order trips up more remodels than any other stretch. The governing rule is simple: cabinets before countertops, because the countertop is measured off the installed cabinets. Flooring timing, by contrast, depends on which floor you chose.

When the flooring goes in

Flooring sequence is driven by the material, not by habit. A continuous, waterproof finished floor under cabinets is the most durable approach in Florida, but a floating floor has different rules.

Floor typeGoes inWhy, in Florida
Porcelain or stone tileBefore cabinetsCreates one waterproof plane; cabinets sit on finished tile, protecting the slab from leaks
Glue-down LVPBefore cabinetsBonded to a moisture-tested slab; cabinets land on the finished surface
Floating SPC vinylAfter cabinetsA floating floor must expand freely; heavy cabinets pinning it cause buckling

For most Florida kitchens we set tile or rigid-core vinyl before the cabinets so the room reads as one sealed surface — but a click-together floating plank is the exception that follows the cabinets instead.

Cabinets first — and why

Cabinet boxes are set, leveled, and fastened to the walls before any stone is measured. They establish the exact horizontal plane and run lengths the countertop must match. Leveling is not cosmetic here: a fabricator templates a flat reference off the cabinet tops, and out-of-level boxes produce a countertop that rocks or gaps.

Countertops: template, then the two-week wait

Only once cabinets are set does a fabricator come to template — a precise physical measurement of the actual installed cabinets, including sink and cooktop cutouts. Templating from drawings instead of installed cabinets is the leading cause of fit problems. After templating, fabrication of the slab runs roughly two weeks before the finished countertop returns for installation.

What templating captures on site

The template records the real geometry the drawings only approximate: the actual cabinet run lengths, out-of-square corners, the sink and cooktop openings, and the overhang. A digital or physical template taken from set cabinets is what lets the shop cut stone that drops in without a refit.

Why fabrication cannot start sooner

Cutting, edge-profiling, and polishing a slab to that template is shop work measured in days, and it cannot begin until the template exists. That is why the two-week window is fixed dead time at the counter — the crew works elsewhere while the stone is fabricated off site.

Cabinets-before-counters, in one check

  1. Are the cabinets set and leveled? If no, the fabricator cannot template — the slab has nothing accurate to measure.
  2. Has the template been taken on site? If no, fabrication cannot start; drawings are not a substitute.
  3. Has fabrication run its ~two weeks? If no, the counter is not ready to set, and the backsplash behind it has to wait too.

That dependency is why a remodel cannot compress the middle: the two-week fabrication window is dead time at the counter, even though the crew keeps moving on other tasks. We break the full stone process down in our countertop templating and fabrication guide.

Phase 9-11: Appliances and Final

With counters set, the backsplash tile goes in against a finished edge, then appliances are connected and the kitchen is tested as a working system before the final inspection signs the permit off.

Backsplash and finish trim

Backsplash tile is installed after the countertop because it lands on top of the counter's back edge. Running it earlier leaves a gap or a cut line that never sits clean. Under-cabinet lighting, hardware, and trim follow in the same finish pass.

Appliance hookup and trim-out

Electricians and plumbers return for trim-out: setting receptacles and switches, connecting the range, dishwasher, disposal, and refrigerator, and confirming the GFCI protection the NEC now requires across kitchen receptacles. This is finish work the rough-in already made possible.

The final inspection

A final building and trades inspection confirms the completed kitchen matches the approved permit and meets code in its finished state. Only a licensed contractor's permit gets a clean final — work done by an unlicensed party, or outside the permit, can stall a sale later. Verifying a contractor's license through the Florida DBPR is the homeowner's safeguard, and a licensed general contractor carries the permit and the final through for you.

How Long a Florida Kitchen Remodel Takes

A full Florida kitchen remodel typically runs 6 to 10 weeks from demolition to final inspection, with the two-week countertop fabrication window built into that span rather than added to it. The variables that stretch a schedule are inspection scheduling, fabrication lead time, and any surprises demo uncovers.

  1. Step1

    Front-load design and permit

    Finalize layout, cabinets, and the EPM plan, then pull the permit before demo. This phase has no on-site disruption, so time spent here is free.

  2. Step2

    Schedule the rough-in inspection early

    Coordinate all three trades to finish together so a single rough-in inspection clears the way for drywall without idle days.

  3. Step3

    Order cabinets to land before the slab template

    Because the two-week fabrication clock starts at template, getting cabinets set on time is the single biggest lever on the finish date.

A general contractor's real value across these weeks is sequencing: booking inspections, staging deliveries, and keeping crews productive during the fabrication gap so the calendar never stalls. The full picture of layout, code, and materials sits in our Florida kitchen remodeling guide, and the structural questions around walls are covered in opening up a kitchen in Florida.

Frequently Asked Questions

What order do you remodel a kitchen in?

A Florida kitchen remodel runs in this order: design, permit, demolition, rough electrical/plumbing/mechanical, the FBC rough-in inspection, insulation and drywall, flooring, cabinets, countertops, backsplash, appliance hookup, and final inspection. The order is fixed because concealed work must be inspected before drywall covers it, and countertops cannot be measured until cabinets are set.

Do cabinets or countertops go in first?

Cabinets go in first, always. A countertop fabricator templates the slab off the installed, leveled cabinet boxes — not off drawings — so the cabinets must be set before any stone is measured. After templating, fabrication runs about two weeks before the finished countertop is installed. Templating from plans instead of installed cabinets is the leading cause of fit problems.

When is flooring installed in a kitchen remodel?

It depends on the floor type. Tile and glue-down vinyl go in before cabinets, so cabinets sit on a finished, waterproof plane that protects the slab — the preferred approach in Florida. A floating SPC plank floor is the exception: it goes in after cabinets, because a floating floor must expand freely and cabinets pinning it can cause buckling.

How long does a kitchen remodel take in Florida?

A full Florida kitchen remodel typically takes 6 to 10 weeks from demolition to final inspection. The roughly two-week countertop fabrication window is built into that span, not added on top. Inspection scheduling, fabrication lead time, and any surprises uncovered during demolition are the factors most likely to stretch the timeline.

What gets inspected during a kitchen remodel?

The key gate is the rough-in inspection of electrical, plumbing, and mechanical work, which must pass before any drywall closes the walls. Many Florida jurisdictions also require an insulation inspection before drywall, and a final building-and-trades inspection confirms the finished kitchen matches the permitted plans and meets code.

Do I need a permit to remodel my kitchen in Florida?

Usually yes, if the work touches the electrical, plumbing, mechanical, gas, or structural systems — adding circuits, moving the sink, or removing a wall all trigger a permit. A cosmetic refresh that leaves utilities alone, such as swapping cabinets in the same footprint or installing a backsplash, often does not. The threshold varies by jurisdiction, and HVHZ counties apply stricter review.

References & Sources

  1. Florida Building Code, Residential — minimum required inspections. https://floridabuilding.org/
  2. City of Tampa — Residential Inspection sequence (rough-in before concealment). https://www.tampa.gov/construction-services/info/inspection-information/residential-inspection
  3. NFPA 70 (National Electrical Code) — Article 210.52 branch-circuit requirements. https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70
  4. Florida Building Code, Residential — Section M1503.4, makeup air for range hoods. https://codes.iccsafe.org/content/FLRC2023P1/chapter-15-exhaust-systems
  5. Florida DBPR — Construction Industry Licensing Board (CILB). https://www.myfloridalicense.com/DBPR/construction-industry/

Done Reading?

Skip Ahead. Get a Free In-Home Estimate.

A Pro Work Flooring project director measures in person, tests the slab where it matters, and sends a written estimate. Statewide Florida service. Manufacturer-certified installers. 5-year workmanship guarantee.

Talk to the Crew